Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Columbia Basin Trust offering business accelerator program

Trust seeking motivated companies for customized support and mentorship program

Trail military exercises provide crucial training

Exercise Sapper Crucible: ‘The nuts and bolts of what a soldier is’

VIDEO: SPCA ushers in new era with Castlegar facility

$2.69-million project had ribbon cutting on Friday

Thrums, Riondel, and Slocan, revisited

Place Names: Scottish author delighted by Thrums name origin

Last stand for Silver City summer

Fall officially arrives in Trail at 6:54 p.m. on Saturday

Conservation officer frees B.C. deer from flotation gear mishap

BC Conservation Officer Service is reminding residents to keep backyards clear of entanglements

VIDEO: B.C.-born firefighter remembered by MP in emotional speech

Family asks first responders to look after one another in wake of suicide, growing concerns of PTSD

Airline has ‘close call’ with drone while en route to B.C. airport

Jazz Aviation reported the drone sighting near Vancouver to the RCMP and Transport Canada

Tragic accident claims life of B.C. toddler

Fundraising effort has been created to help mom and family

B.C. nanny charged with sex abuse of 3 children

Saanich Police seek potential victims of Johnathon Lee Robichaud from Central Saanich

‘I’m no quitter’ on climate change issues, McKenna says at G7 ministers meeting

David Suzuki says if McKenna believes what she’s saying, she too should quit

VIDEO: Inside an eerily empty mall in Canada

Only nine of 517 retail spaces are open for business as the grand opening postponed to next year

B.C. wildfires burned large areas affected by mountain pine beetles: Experts

The mountain pine beetle epidemic affected more than 180,000 square kilometres in B.C.

Tens of thousands without power following tornado in Ottawa region

Hydro Ottawa says more than 170,000 customers were without power early this morning

Most Read