Pipe is staged for twinning the Trans Mountain pipeline, 2019. (Trans Mountain)

COVID-19: Virtual route hearings set for Trans Mountain pipeline

Oral questions, site visits cancelled for 22 B.C. sessions

Detailed route hearings for the B.C. portion of the Trans Mountain pipeline expansion project are going ahead with written submissions and photos from people seeking changes to the route for the twinned oil pipeline.

Procedures have been changed to carry on with the pipeline hearings in the COVID-19 pandemic, for the project approved by the Justin Trudeau government in June 2019. About 70 per cent of the pipeline’s detailed route has been approved, including the entire Alberta portion from Edmonton to Jasper.

The Canada Energy Regulator said April 21 that 22 active detailed hearings remaining along the route between Merritt and Burnaby, the southwestern portion where the original pipeline has operated since 1953. Pipeline construction in Alberta has been paused during spring breakup with about 25 km of twinned pipe still to be installed in the Edmonton area.

Extensive work continues on Trans Mountain’s Burnaby terminal and tank farm, and the nearby Westridge Marine Terminal that is expanding to accommodate up to three Aframax-class oil tankers at a time.

Detailed route hearings are where a commission determines if a valid statement of opposition is filed “that demonstrates a material change in circumstances related to the best possible route of the pipeline, the most appropriate methods of construction or timing of construction,” the Canada Energy Regulator states on its project website.

RELATED: Trans Mountain pipeline begins work in Clearwater

RELATED: Trans Mountain expansion gets green light – again

There are 18 decisions still to be completed for the Fraser Valley-to-Langley portion of the route, with 20 statements of opposition reviewed and another 15 that were denied. One decision remains to be completed for the Surrey-to-Burnaby section, where 16 statements of opposition were denied and two proceeded to the hearing stage.

There are no statements of opposition still active for the Edmonton-to-Jasper portion, or the Hargreaves-to-Blue River segment after the pipeline enters B.C. from Alberta near Valemount. Blue River to Darfield, past Vavenby, Clearwater and Barriere has no decisions left after two statements of opposition were withdrawn following a commission decision.

Black Pines to Wahleach, designated as section five by the federally owned Trans Mountain corporation, runs from north of Kamloops to the Hope and Chilliwack region. It has nine hearing processes that still require a decision as of April 23.

The Canada Energy Regulator announced March 16 that oral portions of all ongoing public hearings would not would not proceed as planned due to the coronavirus pandemic.

“Oral cross-examination in the detailed route hearings will be replaced with written information requests,” the regulator said in an April 21 statement. “The changes will allow detailed route hearings to proceed in a fair and transparent manner, while respecting the physical distance requirements for participants.”


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusTrans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Boundary freshet 2020: At least 189 properties ordered to evacuate as of June 1

Real-time gauges on the West Kettle, Kettle and Granby rivers suggested Monday water near peak

City of Rossland opens playground structures to public

Residents are reminded to drive cautiously in school zones as children head back to school this week

UPDATED: 189 homes in Grand Forks area given evacuation orders

Homes are in the Nursery, Grand Forks Airport, Gilpin Rd., Johnson Flats and Granby Rd. areas

Mercer Celgar announces 30 days of downtime at Castlegar mill in July

Sawlog stumpage charges on pulpwood and complex stumpage rules some reasons for downtime

Flood warning issued for Boundary as Kettle River expected to rise to 20-year return level

RDKB: This amounts to a high flood risk for low-lying properties in the region

VIDEO: A Vancouver Island black bear takes weekend nap in eagle tree

Videos captured by Terry Eissfeldt shows the bear arriving Saturday night and sleeping in on Sunday

George Floyd asphyxiated by sustained pressure: family autopsy

Death sparked a wave of protests across the U.S. and abroad

B.C. Hockey League prepping for 2020-21

League reviewing different scenarios and start times in compliance with provincial regulations

COVID-19: B.C. commercial landlords can’t evict if they decline rent assistance

Emergency order ‘incentive’ for federal program, Carole James says

Investigators probe death of CN employee at Surrey rail yard

Transportation Safety Board is investigating an ‘occurrence that took place during switching operations’

Trans Mountain starts B.C. leg of pipeline twinning project

Mostly finished in Alberta, Burnaby terminal expanding

NDP getting COVID-19 wage subsidy ‘indirectly,’ B.C. Liberal leader says

Andrew Wilkinson says he’s heard no concerns from public

Most Read