Rossland Council updated on cost of fixing arena

It will cost $700,000+ to get job done

An update to city council on the aging Rossland Arena indicates that fixing the facility is going to come with a hefty price tag.

A report to council at its last meeting indicated that replacing the ice-making equipment in the facility and making necessary renovations and repairs to the building itself will cost taxpayers just under $700,000.

That’s nearly double estimates for the project in a report from last fall.

“This time [the estimate] includes installation and engineering,” says Mayor Kathy Moore, explaining the difference. “The other was just the cost of the piece of hardware itself. So we always knew it would be higher.”

The report from city administration giving more detail on the arena project costs was submitted at the Jan. 6 council meeting. Staff said the new estimate includes:

• Required engineering, design and tendering activities (approximately $33,800),

• Actual construction costs (approximately $601,000), and

• Project contingencies (at 10 per cent or $63,480).

However, the estimate isn’t the final bill. Council will get a better sense of — and vote on — the actual cost next month.

“Pricing submitted for completion of this work will be re-reviewed and brought forward to council sometime in February for formal approval due to the lead time of securing applicable components related to completing this project prior to the facility’s 2020/21 operating season,” the report states.

Council’s already started budgeting for the project. The report to council notes that the city’s draft 2020 budget for general arena capital upgrades/undertakings is $537,000 in 2020, and $150,000 for every year between 2021 and 2024.

However, the report to council also notes the estimate is a Class D estimate — the roughest outline of costs — so the final price tag could be even higher.

Staff is working under direction from council to look at replacing the chiller and condenser system for the arena, and adding the capability of having an off-season gym floor to expand the arena’s use.

That motion was made after a public consultation process found most Rosslanders want to keep ice in the arena and find new uses for the facility.

“Both units were installed in 1997 and are considered to be past their expected service life expectancy of 20 years,” says the report to council. “This capital project is also consistent with the future direction of the facility as previously discussed.”

Staff said pricing submitted for completion of this work will be re-reviewed and brought forward to council sometime in February for formal approval.

The decision to begin serious repairs to the arena comes after the facility has had “minimal capital upgrades over the past five to seven years,” the report says. “[T]he city has mainly focused on making it safe to the public and employees to operate and utilize for the short-term.”

The arena was originally built in 1952-53 and in 1955 the Rossland Curling Rink addition was completed. Since the original construction of the facility, numerous additional improvements have been made.

Council received the report as information.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

3 break-ins, copper pipe stolen from vacant Fruitvale school

Village planning future use of the site, including teardown of the old school

Kootenay cold snap ups energy consumption as high as 75 per cent

On Jan. 14, natural gas use rose 50 per cent compared to the previous Tuesday

Introducing 2020 Colombo Lodge executives

Executives were sworn in at an the installation ceremonies earlier this month

Rossland French immersions school to offer high school courses

Expansion decision means students can continue in French to Grade 9

Rossland Council updated on cost of fixing arena

It will cost $700,000+ to get job done

VIDEO: Nickelback gears up for nostalgia tour

Canadian band joins Stone Temple Pilots for a summer tour that includes just one stop in Canada

Province asks health-care staff to be ‘vigilant’ in screening for possible coronavirus cases

This comes after U.S. health officials confirmed a case of the virus in Washington State

Boy, 13, arrested after alleged assault involving girl at B.C. middle school

Boy alleged to have used ‘inappropriate levels of force’ to injure the girl

B.C. player becomes only second Canadian to enter Hall of Fame of Baseball

Walker received 76.6 percent of the Baseball Writers of America Association vote

PHOTOS: Heavy snowfall breaks window, causing avalanche into B.C. newsroom office

It was a chaotic start to the week for the Kitimat Northern Sentinel

Canadian law firm launches class action on behalf of Iran flight victims

Flight 752 was shot down by Iran shortly after take off

Mission Hill cellarman fired after mistakenly dumping $162K of wine down the drain

The former employee filed a grievance with the West Kelowna winery but was unsuccesful

Protesters block B.C. government building entrance to support Wet’suwet’en First Nation

A letter with four demands was delivered to the Ministry of Energy, Mines and Petroleum Resources

Most Read