Ian Anderson, CEO of Kinder Morgan, gestures during an interview at the company’s offices in Calgary in 2016. (THE CANADIAN PRESS/Jeff McIntosh)

Shovels could be in the ground on Trans Mountain by September, CEO says

Ian Anderson points to weeks likely required for NEB to reinstate 2016 regulatory record

The CEO of the Crown corporation building the Trans Mountain pipeline expansion says shovels could be in the ground by September following cabinet approval Tuesday of the long-delayed project.

Oil could be flowing in new segments of the pipeline between Edmonton and the West Coast by mid-2022, Ian Anderson said, about one year later than the timeline envisioned last August when the Federal Court of Appeal quashed its regulatory approval and halted all fieldwork.

“We’re excited, our shippers are excited and the communities we touch are excited along the pipeline corridor,” said the CEO of Trans Mountain Corp. during a conference call Wednesday.

“We’re confident now that our project will meet every standard, every regulation, every test and reflect the values and priorities and principles that we all care for as Canadians.”

The National Energy Board is being asked to reinstate the record from the previous regulatory proceeding in 2016 so that the project can be brought back to the same state of construction readiness as last summer, Anderson said, a process expected to take some weeks.

He said the fact the federal government owns the pipeline won’t change or hurry the process.

Two re-routing requests are still to be decided, he said, including one involving B.C.’s Coldwater reserve, although those processes aren’t expected to affect the timeline.

He said contractors are being mobilized, pipe is being stockpiled in yards in Alberta and B.C. and the Burnaby terminal on the West Coast is being made ready so that construction work can begin there as soon as permitted.

Anderson said there is no update on the last estimated project cost of $7.4 billion, while conceding that “time is money.”

Earlier Wednesday, Finance Minister Bill Morneau told a Calgary business audience the best way to convince a skeptical oilpatch that the expansion will actually be built is to go ahead and build it.

“What we said yesterday was that we renewed that (pipeline) approval,” Morneau told reporters.

“What’s happening today is we’re back at work. The re-permitting is happening starting today. We are going to get work going this construction season. I want people in Alberta and people across the country to know that intent is real.”

Last August, the Federal Court of Appeal ripped up the original federal approval of the 590,000-barrel-per-day expansion, citing incomplete Indigenous consultations and a faulty environmental review.

Dan Healing, The Canadian Press

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Fruitvale product new ambassador for Blue Jays Care Foundation

Fruitvale native Ella Matteucci led off Jays Care Foundation with a few Twitter tips on staying fit

A second wave of COVID-19 is probable, if history tells us anything

B.C.’s top doctor says that what health officials have learned this round will guide response in future

Fact: B.C. bats don’t carry or spread COVID

BC Annual Bat Count goes this summer, citizens encouraged to take part

Mountain Pineapple defers application for new cannabis store in Rossland

The application was originally going to be reviewed by city council on May 19

LIVE: Procession to honour Snowbirds Capt. Jennifer Casey comes to Halifax

Snowbirds service member died in a crash in Kamloops one week ago

One man dead after standoff with Chilliwack RCMP

The Independent Investigations Office of B.C. is investigating the RCMP’s role in the death

B.C. employers worry about safety, cash flow, second wave in COVID-19 restart

A survey found 75 per cent of businesses worry about attracting customers

Ex-BC Greens leader Andrew Weaver says province came close to early election

Disagreement centred on the LNG Canada project in northern B.C.

Canada’s NHL teams offer options to season-ticket holders

Canadian teams are offering refunds, but also are pushing a number of incentives to let them keep the money

B.C. premier says lessons to learn from past racism during response to pandemic

B.C. formally apologized in the legislature chamber in 2008 for its role in the Komagata Maru tragedy

Snowbirds to remain at Kamloops Airport indefinitely after fatal crash

small contingent of the Snowbirds team is staying in Kamloops, acting as stewards of the jets

Oak Bay man stumbles upon eagle hunting seal, grabs camera just in time

The eagle did ‘a perfect butterfly stroke to shore’ with its prey, photographer says

82% of all test-positive COVID-19 cases in B.C. have recovered

B.C. had 303 active cases as of Saturday, May 23

Most Read