The Canadian Press

It’s not too late to pull the plug on Site C: expert

Former civil servant says Newfoundland and Labrador’s dam experience is a warning

A hydroelectric venture in central Labrador should serve as a cautionary tale for B.C. and its own ambitions to build a multibillion-dollar dam in the province’s northeast, the former head of Newfoundland and Labrador’s public utilities regulator says.

David Vardy, a former economics professor and retired civil servant in that province, published a letter Tuesday addressed to the B.C. Utilities Commission containing more than a dozen recommendations based on lessons learned from Muskrat Falls.

READ MORE: Protestors stand for Site C during Clark’s visit

READ MORE: Supreme Court dismisses two Site C lawsuits from B.C. First Nations

The utilities regulator was tasked earlier this month by B.C.’s new NDP government to review the economic viability of Site C, an $8.8-billion energy project under construction on the Peace River.

“B.C. has the luxury of being able to stop this now without going any further,” Vardy said in an interview. “In terms of the take-away from Muskrat Falls: It’s not too late to stop it.”

Vardy’s letter outlined the similarities between the two provinces’ megaprojects: Both are backed by powerful Crown corporations, both were exempt from the usual regulatory oversight process, at least initially, and both have experienced ballooning costs over time.

The price tag for Muskrat Falls has more than doubled from original estimates, swelling to $12.7 billion in the province of only about 525,000 people. Vardy said the project’s cost of about $24,000 per person would double the province’s per capita net debt and pose a major threat to its solvency.

Vardy encouraged B.C.’s Utilities Commission to ensure Site C is built according to current energy needs and is made as adaptable as possible, warning that the rapid pace of technological advances could make the project obsolete before long.

He also emphasized the importance of independent public oversight and a rigorous public review process, lauding the analysis being conducted by the utilities commission.

The review began Aug. 9, with interim findings due six weeks later and a final report expected by Nov. 1.

The commission’s review process in B.C. was once standard before the previous Liberal government’s clean-energy laws permitted some projects, including Site C, to circumvent the regulatory process.

An email from B.C.’s Energy Ministry said the government would consider the results of the report, as well as environmental and First Nations considerations, before making a timely decision on the future of Site C.

Energy Minister Michelle Mungall declined further comment “out of respect for the independence of the review process.”

BC Hydro could not immediately be reached for comment.

The Independent Contractors and Businesses Association told the utilities commission in a statement released Tuesday that BC Hydro must complete Site C.

“The Site C dam has been the subject of a robust, nearly three year, independent review and its business case is solid,” president Chris Gardner said. “We cannot produce this kind of high quality, reasonably priced, clean energy anywhere.”

There are about 2,400 people working on Site C.

Gardner described Site C as an “all-important backbone” that would allow B.C. to transition to other renewable energy sources, adding that ratepayers cannot be expected to spend billions of dollars and get nothing in return.

But Vardy dismissed the logic of chasing money already spent, which he called sunk costs.

“The key consideration must be future costs,” he said.

“We may find it very difficult to walk away from an investment … but what really counts is how much money you’re going to have to spend before you get something that’s worth anything.”

Geordon Omand, The Canadian Press

Just Posted

Trail vet says voting system has worked for 150 years

Letter to the Editor from Vaughn Budd of Trail

Kootenay employers ready to meet job seekers at Black Press career fair

Dozens of companies will attend the event on Nov. 15 at the Ktunaxa Nation Building in Cranbrook

Sandblasting Silver City skate sign

The Trail Sk8 Park was closed on Thursday so workers could ready a sign for painting

Area A seeks views on cannabis rules

The public hearing for Area A residents will go Tuesday, Nov. 13 at 5 p.m.

Trail liquor store held up Friday night

The perpetrator was brandishing a weapon that appeared to be a gun, according to the Trail RCMP

VIDEO: Amazon to split second HQ between New York, Virginia

Official decision expected later Tuesday to end competition between North American cities to win bid and its promise of 50,000 jobs

B.C. cheese linked to 5 E. Coli cases

People are asked to throw out or return ‘Qualicum Spice’ cheese

Canada Post no longer guarantees delivery times amid more rotating strikes

The Canadian Union of Postal Workers closed two major processing centres in Ontario and B.C.

B.C. city councillor resigns as AutismBC director amid SOGI controversy

AutismBC president Gary Robins says Laurie Guerra’s resignation is effective Nov. 12

McGill students vote overwhelmingly to change Redmen team nickname

Student union held a referendum after a campaign by Indigenous students

B.C. university Pride group replaces white supremacy posters

Around 50 people walked through downtown Victoria to share posters of love

B.C. to invest $492 million in affordable homes

72 new projects are part of a 10-year, $1.9-billion strategy

Around the BCHL: Surrey Eagles sliding and Cassidy Bowes flows

Around the BCHL is a look at what’s happening in the league and around the junior A world.

Pit bull cross, chihuahua owners must split costs for dogfight damage, judge rules

Eac side responsible for $577.43 towards injuries in Comox Valley incident

Most Read